By GvilleTX Newsroom
Paving crews could be at work on 18 Denison streets within about two weeks of a council vote, under a roughly $977,000 asphalt overlay proposal from Area Wide Paving, LLC that reached the City Council in its Aug. 17 agenda packet. As of Aug. 26, the city's official record for that meeting carried no minutes or meeting media confirming a recorded approval vote, so the contract's status is not yet documented in the public file.
City staff wrote in the packet that the work would start 10 to 15 days after approval and wrap up by the end of September. Thirteen streets are listed for edge milling and overlay. Five would get cement stabilization under new asphalt.

Public Works drew the list from a recent pavement-condition assessment, according to the packet, ranking streets by poor condition and by how much traffic they carry. The Streets Committee looked the list over June 30 and backed the staff recommendation. The roughest pavement on it is the 200-300 block of W. Munson, scored at 5.3. W. Hull Street, at 50.4, is the soundest street proposed for work. Across roughly 13,800 linear feet of targeted pavement, the average score is about 21.
The quote works out to about $2.09 a square foot for some 468,000 square feet of asphalt, below the $2.50 to $5.00 range Area Wide publishes on its own website for commercial lot paving in Northeast Texas. Denison's overlay status sheet shows about $1.1 million available, $925,000 budgeted plus a $200,000 Ike Hike transfer, and that same money also has to cover a Bullock-Woodlawn paving job and street repair materials.
FY2026 overlay money: what is on hand, what is spoken for
$1,125,000
$925,000 budgeted for street overlay, plus a $200,000 Ike Hike transfer.
$976,553 to Area Wide
Plus $49,940 for Bullock-Woodlawn paving and $98,507 for street repair materials.
Source: Denison FY2026 street-overlay status sheet and expense plan, Aug. 17, 2026 council packet
The current proposal is larger than prior Area Wide overlay items in Denison council records, which show a $619,580 contract approved June 16, 2025, and a $371,336 proposal before the council in July 2024. The Bureau of Transportation Statistics reports highway construction costs rose 63% from fiscal 2021 through fiscal 2025, trimming 32% off what federal infrastructure dollars buy, though that inflation cooled to 0.6% in the most recent year measured, the slowest pace since 2017.
Denison's Area Wide overlay bill has grown every year
The 2024 and 2026 figures are amounts put before the council; the 2025 figure was approved June 16, 2025.
Source: Denison City Council records, CivicClerk
Overlays are maintenance, not reconstruction. The Federal Highway Administration describes pavement preservation as a way to put off costlier rehabilitation while keeping closures shorter than a full rebuild.
Nearby cities also list major street-maintenance costs in their FY2026 plans. Gainesville's Street and Utility Maintenance Program, begun in January 2021 with 175 prioritized improvements, carries a $74.1 million total project cost and about $5.9 million in street spending this fiscal year, with city streets figured for a 30-year life. Sherman's budget page anticipates roughly $20 million in certificates of obligation late this summer for work including Moore Street and Lamberth Road, plus about $4.5 million in tax notes repaid from property-tax revenue.
Area Wide serves Texas through TIPS cooperative contract 23010402, good through April 30, 2027. TIPS requires purchase orders and quotes to cite that contract number.