Sherman's downtown street-lighting project permits the selected contractor to block parking around the Grayson County Courthouse only within the phase then under construction, according to Addendum 1 to the city's bidding documents. The posted record does not establish that Sherman awarded the contract or that crews have started work, and no dated city notice confirms a parking restriction on Travis Street right now.
The city is paying for the job itself. Answering a bidder's question in Addendum 2, Sherman said only city funds are being used. That same document covers excavation of underground conduit trenches and a conduit connection between the courthouse and an equipment pedestal. The advertisement lists sidewalk demolition along with rehabilitation or removal of existing light poles and electrical infrastructure, and calls for parking signs taken out of the work areas to be preserved.

The advertised location is 100 W. Houston Street, the county courthouse in downtown Sherman, which puts the work in Grayson County rather than Cooke. Sherman counts more than 700 parallel and pull-in street spaces downtown, split among one-hour, three-hour and all-day limits, according to the city. The Laurel Street lot has been free for all-day parking since the city discontinued its paid-parking program in May 2025.
Source: City of Sherman, Downtown Parking
Sherman advertised the project May 7, 2026, with bids due June 2. The bidding documents anticipated construction beginning after a council award on either June 15 or July 6. Those dates were prospective, and the records provided do not show that an award or a groundbreaking followed.
Oncor is not supplying the new lights, per Addendum 1, which also requires the contractor to furnish speakers and screens. Asked whether directional boring would be used, the city answered that underground conditions are unknown and that the contractor bears that risk. The contractor must deliver functioning equipment and train city staff, after which Sherman assumes responsibility for operating the system.
The city reestablished its Main Street program in 2016, following a multiyear hiatus, to reach state help with downtown design, grants and planning. The Texas Historical Commission reported in November 2025 that the program has helped 177 communities generate billions of dollars in reinvestment since 1981, a statewide tally rather than a projection for any single project.
Federal Highway Administration guidance credits lighting countermeasures with cutting nighttime pedestrian injury crashes at intersections by about 42 percent. That is research-based general guidance, not a measured or forecast result for replacement lighting in Sherman.
Source: Federal Highway Administration
In Denison, the city's parking guidance lists 10 public downtown lots and free public parking, and tells drivers that the second phase of its downtown reconstruction affects some street parking, with a map showing how to reach businesses. Denison marked completion of its first phase Aug. 7, 2023, and began the second phase May 6, 2024, in the 300 and 400 blocks of Main Street.


Join the conversation
Comments