Sherman capital plan lists $3.8 million to replace failing Texoma Parkway sewer

The city's five-year plan says a development review revealed a failure in an aging clay-tile line near the proposed Peyton Street project.

Sherman's FY2026–2030 capital improvement plan lists about $3.8 million to replace a failing clay-tile sewer on Texoma Parkway near the proposed Peyton Street development. The plan schedules the money across two budget years: $841,900 in FY2027 and $3 million in FY2028.

Workers at an open trench where an underground sewer pipe is being replaced
Sherman's capital plan calls for replacing a failing clay-tile sewer line on Texoma Parkway.

RBerteig / by 2.0

The plan's explanation is brief. An evaluation tied to the development revealed a failure in the line, which the plan describes as nearing the end of its useful life.

| Texoma Parkway sewer replacement | Planned spending |

| --- | ---: |

| FY2027 | $841,900 |

| FY2028 | $3,000,000 |

| Total | $3,841,900 |

Source: City of Sherman FY2026–2030 capital plan

Gainesville's capital plan, adopted Sept. 16, 2025, lists $34,000 in FY2026 for manhole rehabilitation and work to reduce infiltration and inflow, the groundwater and stormwater that seep into sewer lines. It follows with $38,000 a year in each of FY2027 through FY2030. The city's FY2026 budget also reports a 4.5% increase in water and sewer rates and fees under its five-year financial plan, and includes $440,000 for a hydro-jet/vacuum sewer-cleaning truck.

Sherman's plan carries a second sewer item. It allocates $20.532 million across FY2027 through FY2029 to replace and enlarge sewer lines along Post Oak Creek leading to the wastewater treatment plant. The plan states the purpose as accommodating sewer demand from recent and future growth.

$20.532 million

Planned across FY2027–FY2029 to replace and enlarge Post Oak Creek sewer lines leading to Sherman's wastewater treatment plant

The plan says the work is to accommodate sewer demand from recent and future growth.

City of Sherman FY2026–2030 capital plan

Texoma Parkway has appeared in Sherman's sewer planning before. The city's 2018–2023 capital plan identified an overflow risk on the parkway between Sycamore and Evergreen streets and proposed replacing that segment to increase capacity, at an estimated $150,000 from the Utility Improvement Fund. A published draft of the 2020–2025 plan listed overflow relief for the same stretch again, estimated at $200,000 with Greater Texoma Utility Authority financing.

The city's attention to overflows goes back further. Council minutes from March 16, 2009, record a 6–0 vote authorizing engineering services to continue developing a sanitary sewer overflow initiative plan. According to the minutes, the work involved sewer mapping and identifying problems in response to a Texas Commission on Environmental Quality requirement.

The state agency still requires reporting of sanitary sewer overflows regardless of volume, according to TCEQ. Notification is generally due within 24 hours of discovery and a written report within five working days. Qualifying local-government spills of 1,000 gallons or less may instead receive monthly reporting. Reports must describe the cause, volume, duration, potential harm and measures to prevent recurrence.

Denison's published capital-project program includes replacing approximately 3,075 feet of 6-inch sanitary sewer within its 7th Avenue, Hull Street, Murray Street and Johnson Street improvements. Denison says its capital improvements are funded primarily through utility rates and impact fees.

Nationally, the Environmental Protection Agency's 2022 Clean Watersheds Needs Survey identified $630.1 billion in clean-water infrastructure needs over 20 years, measured in January 2022 dollars, including $110.1 billion for repairs to conveyance systems.

$110.1 billion

Documented national need for repairs to sewer conveyance systems over 20 years

Part of $630.1 billion in total clean-water infrastructure needs, in January 2022 dollars. These are documented investment needs, not necessarily unfunded costs.

U.S. EPA, 2022 Clean Watersheds Needs Survey Report to Congress