State filing puts I-35 rebuild through Valley View at about $302 million

The Sept. 16 registration lists construction running from March 2027 into February 2032, while TxDOT's corridor overview still anticipates a 2026 start for the southern Cooke County phase.

Drivers on Interstate 35 through Valley View face roughly five years of construction under a Texas Department of Transportation plan registered this month at about $302 million. The Sept. 16 filing with the Texas Department of Licensing and Regulation covers the Cooke County stretch from FM 3002 to Spring Creek Road, and the registered scope is a full rebuild: main lanes, frontage roads, ramps and cross streets.

The registration lists a March 2027 start and a February 2032 finish. Those are filed plan dates rather than evidence of work underway, and they sit at odds with TxDOT's corridor overview, which still anticipates a 2026 start for the southern Valley View phase.

The TDLR filing identifies TxDOT's Wichita Falls District as owner, Kyle Poirot, P.E., as the owner's contact and Consor Engineers LLC, listed at a Fort Worth address, as designer.

Valley View sits at the south end of a 22-mile program TxDOT carries north to mile marker 1 in Oklahoma. The agency's corridor overview describes an interim design adding a lane in each direction and an ultimate design adding two, and says the northern phase, running from about half a mile south of US 82 to that Oklahoma end point, began construction in the summer of 2024.

A rural stretch of interstate highway with an overpass and frontage roads under an open sky
The registered scope is a full rebuild: main lanes, frontage roads, ramps and cross streets.

Bogdan Migulski / by 2.0

The paperwork reaches back a decade. TxDOT held public meetings in 2015 and 2017, dropped a proposed BNSF railroad realignment in late 2019 and presented a revised design in February 2020 that leaves the tracks where they sit. Federal environmental clearance followed that December.

Corridor traffic in the 2020 federal environmental record: about 56,300 vehicles a day in the 2015 baseline, projected near 92,350 by 2045, with trucks about a fifth of peak-hour traffic.

Four records carry a dollar amount for the segment, each on a different basis.

| Record | Basis | Figure |

| --- | --- | --- |

| TxDOT rural transportation presentation, May 2024 | Project estimate, FY2026 letting | $195 million |

| 2025–2028 STIP revision, Sept. 2024 | Construction cost / total project cost | About $222 million / $281.3 million |

| Draft 2026 Unified Transportation Program | Draft planning figure | $361.2 million |

| TDLR registration, Sept. 16, 2026 | Registered construction estimate | $301.9 million |

The draft program figure is a planning number, separate in basis from the construction estimate filed with TDLR. The 2024 statewide revision's funding table showed federal and state dollars covering the work, with no local match.

Valley View is the second-priciest I-35 job on this stretch of the corridor

The chart loads when visible. All values are in the table.

Totals cover segments of different length and scope; the US 82–Oklahoma figure includes new Red River bridges, and the Denton County job lies south of Cooke County.

TxDOT Wichita Falls District profile; TxDOT Denton County construction report, early 2026; TDLR registration, Sept. 16, 2026

The newly registered Valley View segment

View as a table
LabelCost ($ millions)
US 82 to Oklahoma482 $ millions
Valley View: FM 3002–Spring Creek301.9 $ millions
US 82 to S. of Spring Creek210 $ millions
Denton Co.: FM 455–View Rd170.7 $ millions

The 2020 corridor fact sheet tells landowners what TxDOT anticipated: about 124 acres of added right-of-way across 163 parcels and possible displacement of six commercial structures, figures that cover the whole corridor rather than the registered segment alone. That design would also replace discontinuous two-way frontage roads with continuous one-way roads, with crossovers about every mile and a half.

124 acres

of additional right-of-way anticipated for the I-35 corridor

Across 163 parcels, with possible displacement of six commercial structures. These are corridor-wide estimates from 2020, not figures for the registered Valley View segment alone.

TxDOT I-35 corridor fact sheet, September 2020

Closer to home, Gainesville announced Sept. 13 that contractors would pull old railroad tracks out of North Dixon Street near the 1200 block, between Tony's Feed & Seed and Red River Co-op, and replace the roadway with concrete. The city set the work for Sept. 14 through 21, weather permitting, with crews rebuilding half the street at a time and letting the concrete cure before switching sides to keep the road and the businesses open.