GvilleTX

Text size

Reading size
Light or dark

Ask GvilleTX

Back to News
GvilleTX ReportingLocal News

State approves $8 million loan for Lake Kiowa water-main replacement

The repayable state financing pays for the next round of pipe work on a system first laid in 1967. Residential minimum bills have risen about $30 a month since 2024.

The Lake Kiowa Special Utility District has state approval to borrow about $8 million to replace roughly 5 more miles of aging water main on the east side of Lake Kiowa, about seven miles southeast of Gainesville. The Texas Water Development Board approved the financing on Sept. 18, 2025. Its announcement and meeting agenda show the money covers the work from planning through construction.

The money must be repaid. It comes from the Texas Water Development Fund, which makes fixed-rate loans that usually run 20 to 30 years and offers no grants or principal forgiveness, according to the fund's program guidance. The approval went to the Greater Texoma Utility Authority, acting for the district. The board estimated the district could save about $1.4 million over the loan's life by borrowing from the state. A July 2024 state board briefing put 2024 requests to a separate program, the Drinking Water State Revolving Fund, at more than seven times that program's capacity.

Customers are already paying more. District rate notices show that residential customers on three-quarter-inch and one-inch meters now pay a monthly minimum about $30 higher than in 2024, with most of the jump in January 2025. The notice for a smaller increase in January 2026 cited operating costs and debt payments for current and future replacement projects.

Most of the rate jump came in 2025

The chart loads when visible. All values are in the table.

Residential monthly minimum for three-quarter-inch to one-inch meters, by the year each rate took effect on Jan. 1.

Lake Kiowa Special Utility District residential rate change notices, January 2024, January 2025 and January 2026

The steepest increase

View as a table
Year rate took effectMonthly minimum (dollars)
202477.39 dollars per month
2025102.93 dollars per month
2026108.08 dollars per month

The board's project assessment says the system dates to 1967 and includes asbestos-cement pipe. The district serves about 2,900 residents. It estimates about 40 line breaks and about 9 million gallons of water loss each year.

The program has cost more than first planned. In November 2024, the district reported that four of six phases had replaced slightly more than half its lines for about $14 million, the original estimate for the whole program. A rate notice that month put Phase 5 at about $6 million. Minutes in a September 2025 Greater Texoma Utility Authority meeting packet attribute the higher figure to rising material and construction costs and record a unanimous vote to seek the larger amount.

$8.015 million

State financing approved for Phase 5, up from a $6.2 million estimate

The district's November 2024 rate notice estimated Phase 5 at $6.2 million. Greater Texoma Utility Authority minutes attribute the increase to higher material and construction costs.

Texas Water Development Board, Sept. 18, 2025; Lake Kiowa Special Utility District rate change notice, November 2024; Greater Texoma Utility Authority meeting packet, Sept. 15, 2025

The district had planned to delay Phase 5. In December 2024, it said that breaks rose after a dry summer and fall, so it moved the work forward. On April 9, 2025, its board approved CobbFendley for the engineering, with every director present voting yes, according to the minutes.

The same December statement said Phase 4 pipe bursting disturbed more ground than expected because old lines were shallower or in different places than drawings showed. The district committed to boring on future work. A Sept. 9, 2026, district update named Blackrock Construction as contractor and said crews would bore new line through easements across the street from the old mains. It projected a Sept. 1 start but did not confirm work had begun.

In December 2024, the district said its Phase 6 lines are just as old but have broken less often, which could let that last phase wait.

Join the conversation

Keep up with Gainesville

State approves $8 million loan for Lake Kiowa water-main replacement | GvilleTX